Activity 4-5 in a Network Diagram Has an Optimistic Time

question 32

Multiple Choice

Activity 4-5 in a network diagram has an optimistic time estimate of five days, a most likely time estimate of seven days, and a pessimistic time estimate of 10 days.Its expected time is approximately: