The Use of 6:30

question 78

Short Answer

The use of 6:30
A.M.The meetings continued for about two weeks until the project got back on schedule.At that time the project manager announced that the next meeting was canceled, and no further sunrise meetings were ever scheduled.
A.M.meetings to get a project back on schedule is an example of ______ reinforcement to motivate project performance.
The project manager does not have direct authority over many key people, especially the contractors from the other companies.They do, however, have the freedom to convene meetings at his convenience.So the project manager will institute daily "coordination meetings," which were required of all the principals involved, at 6:30