If Testing Cannot Be Completed Any Earlier Than Four Days

question 89

Multiple Choice

If testing cannot be completed any earlier than four days after the prototype is built, which of the following type of lag exists?


Definitions:

Critical Path

The sequence of tasks that determines the minimum project duration; delaying any task on this path delays the whole project.

Project Duration

The total period from the start to the completion of a project.

Negative Total Float

The amount of time that needs to be saved on a project schedule to meet the deadline, indicating a project is behind schedule.