Noah Construction Company Is Building a Large Complex for a Contract

question 127

Multiple Choice

Noah Construction Company is building a large complex for a contract price of $5,000,000. This is a three-year project estimated to cost $4,000,000 and the following information is available:
($ in thousands)   Year 1  Year 2  Year 3  Costs incurred $1,000$1,500$1,250 Estimated completion costs $3,000$1,500$10 Billings $750$1,750$2,500 Cash collected $500$1,500$3,000\begin{array}{llll}(\$ \text { in thousands) } & \text { Year 1 } & \text { Year 2 } & \text { Year 3 }\\\text { Costs incurred } & \$ 1,000 & \$ 1,500 & \$ 1,250 \\\text { Estimated completion costs } & \$ 3,000 & \$ 1,500 & \$ 10 \\\text { Billings } & \$ 750 & \$ 1,750 & \$ 2,500 \\\text { Cash collected } & \$ 500 & \$ 1,500 & \$ 3,000\end{array}
-Using the percentage-of-completion method of revenue recognition,how much income is recognized in Year 3?


Definitions:

Estimate At Completion

A forecasting tool used in project management to predict the total cost of a project at its completion.

Budgeted Cost

The estimated financial expenditure for a project, activity, or operation, typically set during the planning phase.

Planned Value

In project management, it represents the estimated monetary value of the work planned to be done on a project at a given point in time.

Budget At Completion

The total budgeted cost of a project at its completion, including all planned expenditures and liabilities.

Related Questions