Quality Exteriors installs stucco on high-priced custom homes, using the time-and-materials method to price jobs for individual builders. Quality anticipates using $250,000 of materials during the year and will incur $15,000 for material handling and storage. Other overhead costs, which are driven by the company's 18,000 direct labor hours, will total $360,000. Quality pays construction crews $17 per labor hour and adds a markup of $19 per hour on its time charges. There is no profit markup on material cost.
During the first quarter of the year, Quality performed 24 jobs for Don Henderson Builders, using 3,100 labor hours and $72,000 of materials.
Required:
Calculate the amount that Quality would bill Don Henderson Builders for work performed.
Q2: Which of the following individuals is least
Q6: When allocating joint costs,Weinberg calculates the final
Q9: Martin Company,which applies overhead to production on
Q20: Which of the following measures of performance
Q42: What price will the company charge if
Q43: Nash Corporation allocates administrative costs on the
Q71: Several executive levels typically are involved in
Q85: Which of the following elements is not
Q90: A company's sales forecast would likely not
Q91: An unlimited-payment plan for controlling sales force