Scrum Relies on Three Key Roles

question 96

Multiple Choice

Scrum relies on three key roles.A person who acts on behalf of customers to represent their interests and who is responsible for ensuring that the development team focuses their efforts on developing a project that will fulfill the business objective of the project is called a