Compute the slack for the following project.
Activity A has a duration of 4 days and no predecessor.
Activity B has a duration of 2 days and has A as a predecessor.
Activity C has a duration of 2 days and has A as a predecessor.
Activity D has a duration of 3 days and has B as a predecessor.
Activity E has a duration of 4 days and has C as a predecessor.
Activity F has a duration of 1 day and has D and E as predecessors.
Invitation To Treat
An Invitation to Treat is a legal expression signaling the initiation of negotiations, inviting offers which can then be accepted or rejected by the party issuing the invitation.
Reward
An offer of compensation for providing assistance, such as returning lost property or providing information leading to fulfilling certain conditions.
Offer
A proposal by one party to another intending to create a legally binding contract if accepted.
Accept
To agree to the terms of an offer or contract, creating a binding legal agreement.
Q2: At the strategic level,the concepts,tools,and techniques used
Q3: The principle that is most likely to
Q6: Describe three factors that contribute to MRP
Q18: Explain in brief the role and function
Q46: Describe the objective of the newsvendor problem.
Q47: Which of the following statements is true
Q50: Industry uses both AON and AOA for
Q59: Describe a reliability analysis.
Q63: Outsourcing generally gives an organization more control
Q72: Competitive pressures generally are reduced as additional