Funtime Corporation Assume That Funtime Corp

question 75

Multiple Choice

Funtime Corporation Assume that Funtime Corp.has agreed to construct a new playground for Durrey County for $2,300,000.Construction of the new playground will begin on March 17,2012 and is expected to be completed in August 2013.At the signing of the contract Funtime Corp.estimates that the it will cost $1,600,000 to build the playground.
At the end of 2012 Funtime provided the following information about the project:
Funtime Corporation Assume that Funtime Corp.has agreed to construct a new playground for Durrey County for $2,300,000.Construction of the new playground will begin on March 17,2012 and is expected to be completed in August 2013.At the signing of the contract Funtime Corp.estimates that the it will cost $1,600,000 to build the playground. At the end of 2012 Funtime provided the following information about the project:   What percentage is playground complete? A)  62.5% B)  43.5% C)  55.6% D)  50.0% What percentage is playground complete?


Definitions:

Steam Engine

A heat engine that performs mechanical work using steam as its working fluid.

Invented

The process of creating or designing something that did not previously exist, often referring to the conception of new ideas, devices, or methods.

Invention Hazards

The potential risks or unintended negative consequences associated with the creation and implementation of new inventions or technologies.

Normal Accidents

Refers to complex systems' inevitable incidents caused by their intricacies and interactive elements, often unpredictable.

Related Questions