Playtime Corporation
Assume That Playtime Corp What Percentage Is the Playground Complete?
A) 62

question 75

Multiple Choice

Playtime Corporation
Assume that Playtime Corp.has agreed to construct a new playground for Surrey County for $2,450,000.Construction of the new playground will begin on March 17, 2012 and is expected to be completed in August 2013.At the signing of the contract Playtime Corp.estimates that it will cost $1,750,000 to build the playground.
-At the end of 2012 Playtime provided the following information about the project:
 Costsincurred  Estimated costs  Year  to date  remaining 2012$1,200.000$600.000\begin{array}{lll} & \text { Costsincurred } & \text { Estimated costs } \\\text { Year }&\text { to date } & \text { remaining }\\2012&\$ 1,200.000 & \$ 600.000 \\\end{array}
What percentage is the playground complete?


Definitions:

Pasta Bake Sauce

A type of sauce specially formulated or recommended for use in oven-baked pasta dishes.

Target Audience

A specific group of consumers identified as the intended recipient of a product, service, or marketing campaign.

Horse And Buggy

A traditional mode of transportation using a horse-drawn carriage; often associated with historical or rural settings.

Discontinuous Innovation

A form of innovation that creates a significant change in the way a market functions, often leading to the creation of entirely new markets.

Related Questions