OM Construction Company must choose between two types of cranes.Crane A costs $600,000,will last for five years,and will require $60,000 in maintenance each year.Crane B costs $750,000,will last for seven years,and will require $30,000 in maintenance each year.Maintenance costs for cranes A and B occur at the end of each year.The appropriate discount rate is 12% per year.Which machine should OM Construction purchase?