A project can have a negative Schedule Variance and still be ahead of schedule when
A.All budget targets have been achieved.
B.Non-Critical task delays are greater than progress on the Critical Path.
C.Progress on the Critical Path is faster than non-critical path tasks.
D.None of these choices are correct.