Without Any Formal Planning, the President of a Software Company

question 53

Multiple Choice

Without any formal planning, the president of a software company remarks in a speech that new technologically advanced software will be available in one year.This may lead to a project that must be done faster than anticipated.This is an example of reducing project duration caused by