Emily has recently learned that she needs to reduce the duration of her project to meet an imposed deadline.She has calculated the crash cost per unit and knows the maximum units each activity can be reduced.What is the next step?
Subgoaling
The process of breaking down a larger goal into smaller, more manageable objectives.
Planning
The cognitive process of thinking about and organizing the activities required to achieve a desired goal.
Heuristics
Mental shortcuts or rules of thumb that simplify decision-making processes.
Algorithms
Instructions or procedures designed to solve a specific problem or perform a specific task through a series of steps, pivotal in programming and technology.
Q2: A good starting point for developing time
Q28: An activity cannot begin until ALL preceding
Q30: Sam is the coach of a high
Q32: When project teams get too used to
Q47: Discuss how key practices in the partnering
Q58: Too many parallel activities for one individual
Q61: When completing the forward pass, the project
Q66: There are fewer options available for reducing
Q86: Refining Estimates may be necessary for a
Q97: Because most project work is a collaborative