When Using Resource-Constrained Scheduling, Activities That Were Once Scheduled to Be

question 8

Essay

When using resource-constrained scheduling, activities that were once scheduled to be completed at the same time now may have to be scheduled in sequence. What are the "rules of thumb" or heuristics that need to be followed to determine which activity is scheduled first?