The four tasks below must be completed in order (a single path of tasks) .Given the task information, what is the probability that the path of tasks will be completed in 20 days or less? The four tasks below must be completed in order (a single path of tasks) .Given the task information, what is the probability that the path of tasks will be completed in 20 days or less?   A) 34 days B) 56.4% C) 50% D) 76.0%