Examlex

Solved

Task X Is Expected to Take 3 Days to Complete

question 4

Multiple Choice

Task X is expected to take 3 days to complete.The maximum (latest) earliest finish date for any predecessors to task X is 10.Therefore, the earliest finish for task X is: