Identify the false statement.


Definitions:

Crashing

The process of expediting project completion typically by adding more resources or by working extra hours, often resulting in increased costs.

Critical Path

The sequence of tasks that determines the minimum completion time for a project, where any delay will result in a delay of the entire project.

Project Completion Date

The specifically scheduled date by which all work on a project is expected to be completed.

Crashing

A project management technique that involves adding additional resources to critical tasks to shorten the project duration.