In an MRP Problem, a Is an MPS Item

question 67

Multiple Choice

In an MRP problem, A is an MPS item.Every A requires 2 B's and 3 C's.Every B requires 5 C's. All lead times are two periods.All initial inventory values are 0.Use lot-4-lot method for order quantities for all items.What is the low level code (LLC) for B and C?


Definitions: