Consider the Following Work Breakdown Structure What Is the Probability That This Project Will Be Completed

question 106

Multiple Choice

Consider the following work breakdown structure:  Time Estimates (days)   Activity  Precedes  Optimistic  Most Likely  Pessimistic  Start  A, B, C  A  D 385062 B  E 9099108 C  End 85100115 D  F 192531 E  End 91100115 F  End 626568\begin{array}{l}\begin{array} { c c c c c } &&&\text { Time Estimates (days) }\\\text { Activity } & \text { Precedes } & \text { Optimistic } & \text { Most Likely } & \text { Pessimistic } \\\hline \text { Start } & \text { A, B, C } & - & - & - \\\text { A } & \text { D } & 38 & 50 & 62 \\\text { B } & \text { E } & 90 & 99 & 108 \\\text { C } & \text { End } & 85 & 100 & 115 \\\text { D } & \text { F } & 19 & 25 & 31 \\\text { E } & \text { End } & 91 & 100 & 115 \\\text { F } & \text { End } & 62 & 65 & 68\end{array}\end{array} What is the probability that this project will be completed within 205 days?


Definitions:

Service Level

A measure of the quality of service provided by a business, often evaluated against customer expectations or industry standards.

Single-Period Order Model

A decision-making tool used in inventory management for products with a limited lifespan, focusing on optimizing order quantities for a single selling period.

Christmas Trees

In the context of oil and gas, refers to the assembly of valves, spools, and fittings installed on a wellhead to control the flow of oil or gas from the well.

Inventory Ordering

The process of determining the optimal quantity and timing of orders for products or materials to meet demand while minimizing costs.

Related Questions