Consider the Following Work Breakdown Structure What Is the Estimated Slack Time for Activity E?
A)

question 134

Multiple Choice

Consider the following work breakdown structure:  Time Estimates (wks)   Start  Finish  Activity  Node  Node t0tmtp A 12112029 B 23258 C 24183042 D 3471013 E 14314043\begin{array}{r}{\text { Time Estimates (wks) }} \\\begin{array}{lccccc}& \text { Start } & \text { Finish } \\\text { Activity } & \text { Node } \quad\quad& \text { Node } \quad\quad& \mathrm{t}_{0} \quad\quad& \mathrm{t}_{\mathrm{m}} \quad& \mathrm{t}_{\mathrm{p}} \quad\\\hline \text { A } & 1 & 2 & 11 & 20 & 29 \\\text { B } & 2 & 3 & 2 & 5 & 8 \\\text { C } & 2 & 4 & 18 & 30 & 42 \\\text { D } & 3 & 4 & 7 & 10 & 13 \\\text { E } & 1 & 4 & 31 & 40 & 43\end{array}\end{array} What is the estimated slack time for activity E?


Definitions:

IQ

An abbreviation for Intelligence Quotient, a score derived from standardized tests designed to measure human intelligence.

Sociobiologists

Scientists who study the biological basis of all forms of social behavior, including those of humans, in the context of evolution.

Evolved Biological Tendencies

Evolved biological tendencies are innate predispositions or behaviors that have developed over time to adapt to environmental challenges for survival.

Bell-shaped Curve

A graphical representation of a normal distribution, showing how data points are symmetrically distributed around the mean.

Related Questions