Using the Information Given in the Following Table (A) Identify the Critical Path

question 19

Essay

Using the information given in the following table:  Activity  Precedes  Duration  Start  a, b, c  a  d 5 d  f 6 f  g 2 b  e 5 e  f 9 c  h 4 h  g, i 6 g  end 3 I  end 1\begin{array}{lll}\text { Activity } & \text { Precedes } & \text { Duration } \\\hline \text { Start } & \text { a, b, c } & - \\\text { a } & \text { d } & 5 \\\text { d } & \text { f } & 6 \\\text { f } & \text { g } & 2 \\\text { b } & \text { e } & 5 \\\text { e } & \text { f } & 9 \\\text { c } & \text { h } & 4 \\\text { h } & \text { g, i } & 6 \\\text { g } & \text { end } & 3 \\\text { I } & \text { end } & 1\end{array} (A) Identify the critical path.
(B) Determine expected project duration.


Definitions:

Critical Period

A specific time in development when the presence or absence of certain experiences or stimuli has a long-lasting influence on the individual.

Critical Period

A specific time frame during the development of an organism when it is particularly sensitive to certain environmental stimuli that are necessary for proper development.

Scientific Method

A way to answer questions using empirical research and data-based conclusions.

Framingham

A city in Massachusetts known for the Framingham Heart Study, a long-term, ongoing cardiovascular cohort study.

Related Questions