In the project network presented below, numbers on each arrow refer to the expected time and standard deviation in weeks for that particular activity. For example, "8,2" indicates an activity with an expected time of 8 and a standard deviation of two weeks. In the project network presented below, numbers on each arrow refer to the expected time and standard deviation in weeks for that particular activity. For example,  8,2  indicates an activity with an expected time of 8 and a standard deviation of two weeks.   For this project, determine each of the following: (A) the activities which are on the critical path (B) the expected project duration (C) the probability that the project will be completed in 29 weeks or less For this project, determine each of the following:
(A) the activities which are on the critical path
(B) the expected project duration
(C) the probability that the project will be completed in 29 weeks or less


Definitions:

Expectations

Beliefs or predictions about future events, often based on previous experience or societal standards.

Obligations

Duties or commitments that one is bound to, usually due to legal, moral, or personal reasons.

Sense of Purpose

The feeling of having a goal or determination in life.

Diffidence

A trait of lacking confidence in oneself and being hesitant in asserting oneself.

Related Questions