Consider the Following Work Breakdown Structure What Are the Estimated Expected (Mean) Times (In Weeks) for Duration

question 100

Short Answer

Consider the following work breakdown structure:  Duration Estimate (Days)  Start  Finish  Activity  Node  Node  Optimistic  Most Likely  Pessimistic  A 1291521 B 13132123 C 246918 D 25233547 E 35192627 F 46232941 G 56142026 H 67258\begin{array}{r} \text { Duration Estimate (Days) }\quad \quad \quad \quad \\\begin{array}{lccccc} & \text { Start } & \text { Finish } \\\text { Activity } & \text { Node } & \text { Node } & \text { Optimistic } & \text { Most Likely } & \text { Pessimistic } \\\hline \text { A } & 1 & 2 & 9 & 15 & 21 \\\text { B } & 1 & 3 & 13 & 21 & 23 \\\text { C } & 2 & 4 & 6 & 9 & 18 \\\text { D } & 2 & 5 & 23 & 35 & 47 \\\text { E } & 3 & 5 & 19 & 26 & 27 \\\text { F } & 4 & 6 & 23 & 29 & 41 \\\text { G } & 5 & 6 & 14 & 20 & 26 \\\text { H } & 6 & 7 & 2 & 5 & 8\end{array}\end{array} What are the estimated expected (mean) times (in weeks) for activities A-H?


Definitions:

Violent TV

Television content that includes scenes of physical or aggressive behavior intended to cause harm.

Orient

To align or position something relative to points of reference or to familiarize oneself with a particular situation or environment.

Habituation

A mental conditioning process where the reaction to a stimulus reduces due to its repeated presentation.

Sensitization

the process of becoming more sensitive to a particular stimulus over time, particularly in the context of allergy or immune response.

Related Questions