Consider the Following Work Breakdown Structure In Crashing This Project to 18 Weeks, Which Activities (In

question 84

Essay

Consider the following work breakdown structure:  Activity  Precedes  Normal  Time (wks)  Crashing  Cost (1st  week )(2nd  week)  Start  A, B  A  C, D 68 B  G 456 C  E 4 D  F 566 E  H 688 F  H 6710 G  I 835 H  End 51215 I  End 65\begin{array} { l c c c c } \text { Activity } & \text { Precedes } & \begin{array} { c } \text { Normal } \\\text { Time (wks) }\end{array} & \begin{array} { c } \text { Crashing } \\\text { Cost } \left( 1 ^ { \text {st } } \text { week } \right)\end{array} & \left( 2 ^ { \text {nd } } \right. \text { week) } \\\hline \text { Start } & \text { A, B } & - & - & - \\\text { A } & \text { C, D } & 6 & 8 & - \\\text { B } & \text { G } & 4 & 5 & 6 \\\text { C } & \text { E } & 4 & - & - \\\text { D } & \text { F } & 5 & 6 & 6 \\\text { E } & \text { H } & 6 & 8 & 8 \\\text { F } & \text { H } & 6 & 7 & 10 \\\text { G } & \text { I } & 8 & 3 & 5 \\\text { H } & \text { End } & 5 & 12 & 15 \\\text { I } & \text { End } & 6 & 5 & -\end{array} In crashing this project to 18 weeks, which activities (in order of selection) will be reduced?


Definitions:

Flashbulb Memories

Highly detailed, vivid memories of a moment or event that are believed to be encoded in the brain as a result of the emotional significance or shock of the event.

Weaver

A term that could refer to an individual who creates fabric by weaving fiber, or metaphorically to someone who combines elements into a cohesive whole; without specific context, a broader definition cannot be provided accurately.

Encoding

The cognitive process(es) by which information is translated into a mental or internal representation and stored.

False Memory

A psychological phenomenon where a person recalls something that did not happen or recalls it differently from the way it actually happened.

Related Questions