Consider the Following Work Breakdown Structure What Is the Estimated Standard Deviation in the Time for c

question 3

Multiple Choice

Consider the following work breakdown structure:  Time Estimates (days)   Activity  Precedes  Optimistic  Most Likely  Pessimistic  Start  A, B, C  A  D 385062 B  E 9099108 C  End 85100115 D  F 192531 E  End 91100115 F  End 626568\begin{array}{l}\begin{array} { c c c c c } &&&\text { Time Estimates (days) }\\\text { Activity } & \text { Precedes } & \text { Optimistic } & \text { Most Likely } & \text { Pessimistic } \\\hline \text { Start } & \text { A, B, C } & - & - & - \\\text { A } & \text { D } & 38 & 50 & 62 \\\text { B } & \text { E } & 90 & 99 & 108 \\\text { C } & \text { End } & 85 & 100 & 115 \\\text { D } & \text { F } & 19 & 25 & 31 \\\text { E } & \text { End } & 91 & 100 & 115 \\\text { F } & \text { End } & 62 & 65 & 68\end{array}\end{array} What is the estimated standard deviation in the time for activity E?


Definitions:

Renunciation

Occurs when either party manifests to the other that he does not wish the agency to continue. This is done by the agent.

Revocation

The act of withdrawing, cancelling, or annulling a legal right, license, or agreement formally and officially.

Personnel Manager

A professional responsible for overseeing the recruitment, training, and welfare of employees.

Management Trainee

A management trainee is an individual in an entry-level position, undergoing training and performing tasks under supervision to learn the skills necessary for management positions.

Related Questions