Consider the Following Work Breakdown Structure What Is the Probability That the Critical Path for This

question 53

Multiple Choice

Consider the following work breakdown structure:  Time Estimates (days)   Activity  Precedes  Optimistic  Most Likely  Pessimistic  Start  A, B  A  C, D 445056 B  D 456075 C  E 424548 D  F 314049 E  F 273639 F  End 587082\begin{array}{l}\begin{array} { l c c c c } &&&\text { Time Estimates (days) }\\\text { Activity } & \text { Precedes } & \text { Optimistic } & \text { Most Likely } & \text { Pessimistic } \\\hline \text { Start } & \text { A, B } & - & - & - \\\text { A } & \text { C, D } & 44 & 50 & 56 \\\text { B } & \text { D } & 45 & 60 & 75 \\\text { C } & \text { E } & 42 & 45 & 48 \\\text { D } & \text { F } & 31 & 40 & 49 \\\text { E } & \text { F } & 27 & 36 & 39 \\\text { F } & \text { End } & 58 & 70 & 82\end{array}\end{array} What is the probability that the critical path for this project will be completed within 210 days?


Definitions:

Consolidated Statement

A financial statement that integrates the assets, liabilities, and operating results of a parent company and its subsidiaries.

Carrying Value

The value at which an asset is recognized on the balance sheet, factoring in depreciation, amortization, and impairment charges.

Fair Value

An estimate of the price at which an asset or liability could be traded in a current transaction between willing parties, other than in a forced or liquidation sale.

Goodwill

represents the excess of the purchase price over the fair value of the net assets of the acquired company in a business combination.

Related Questions