Consider the Following Work Breakdown Structure What Is the Estimated Expected (Mean) Time for Activity Y

question 110

Multiple Choice

Consider the following work breakdown structure:  Duration Estimates (Days)   Activity  Precedes  Optimistic  Most Likely  Pessimistic  Start  U, V  U  W 355065 V  W, X 284052 W  Z 263544 X  Y 284052 Y  Z 262938 Z  End 366084\begin{array}{r}\text { Duration Estimates (Days) }\quad\quad\quad\\\begin{array} { l c c c c } \text { Activity } & \text { Precedes } & \text { Optimistic } & \text { Most Likely } & \text { Pessimistic } \\\hline \text { Start } & \text { U, V } & - & - & - \\\text { U } & \text { W } & 35 & 50 & 65 \\\text { V } & \text { W, X } & 28 & 40 & 52 \\\text { W } & \text { Z } & 26 & 35 & 44 \\\text { X } & \text { Y } & 28 & 40 & 52 \\\text { Y } & \text { Z } & 26 & 29 & 38 \\\text { Z } & \text { End } & 36 & 60 & 84\end{array}\end{array} What is the estimated expected (mean) time for activity Y?


Definitions:

Written Word

Information or content that is expressed in written form, as opposed to spoken word or other modes of communication.

Advertised Reward

An offer of payment published to the general public for the performance of a specific task, such as information leading to the recovery of lost property.

Express Mail

Express Mail is a service that provides expedited mail delivery, often guaranteeing delivery by a specific time the following day or within a specified period.

Acceptance

In contract law, the agreement by a party to the terms of an offer, thereby creating a binding contract.

Related Questions