Consider the Following Work Breakdown Structure What Is the Estimated Slack Time for Activity W?
A)

question 25

Multiple Choice

Consider the following work breakdown structure:  Duration Estimates (Days)   Activity  Precedes  Optimistic  Most Likely  Pessimistic  Start  U, V  U  W 355065 V  W, X 284052 W  Z 263544 X  Y 284052 Y  Z 262938 Z  End 366084\begin{array}{r}\text { Duration Estimates (Days) }\quad\quad\quad\\\begin{array} { l c c c c } \text { Activity } & \text { Precedes } & \text { Optimistic } & \text { Most Likely } & \text { Pessimistic } \\\hline \text { Start } & \text { U, V } & - & - & - \\\text { U } & \text { W } & 35 & 50 & 65 \\\text { V } & \text { W, X } & 28 & 40 & 52 \\\text { W } & \text { Z } & 26 & 35 & 44 \\\text { X } & \text { Y } & 28 & 40 & 52 \\\text { Y } & \text { Z } & 26 & 29 & 38 \\\text { Z } & \text { End } & 36 & 60 & 84\end{array}\end{array} What is the estimated slack time for activity W?


Definitions:

Euphoria

A state of intense happiness and self-confidence, often more than is appropriate in a given situation, sometimes caused by drugs or manic episodes.

Appetite

The natural desire to satisfy a bodily need, especially for food.

Opiates

A group of drugs derived from opium that are used for their analgesic (pain relief) properties, but can also be addictive.

Euphoria

A feeling or state of intense excitement and happiness.

Related Questions