Consider the Following Work Breakdown Structure What Is the Total Cost of Reducing This Project by c

question 42

Short Answer

Consider the following work breakdown structure:  Activity  Precedes  Normal  Time (wks)  Crashing  Cost (1st  week) (2nd  week)  Start  A, B  A  C, D 68 B  G 456 C  E 4 D  F 566 E  H 688 F  H 6710 G  I 835 H  End 51215 I  End 65\begin{array} { l c c c c } \text { Activity } & \text { Precedes } & \begin{array} { c } \text { Normal } \\\text { Time (wks) }\end{array} & \begin{array} { c } \text { Crashing } \\\text { Cost } \left( 1 ^ { \text {st } } \right. \text { week) }\end{array} & \left( 2 ^ { \text {nd } } \right. \text { week) } \\\hline\text { Start } & \text { A, B } & - & - & - \\\text { A } & \text { C, D } & 6 & 8 & - \\\text { B } & \text { G } & 4 & 5 & 6 \\\text { C } & \text { E } & 4 & - & - \\\text { D } & \text { F } & 5 & 6 & 6 \\\text { E } & \text { H } & 6 & 8 & 8 \\\text { F } & \text { H } & 6 & 7 & 10 \\\text { G } & \text { I } & 8 & 3 & 5 \\\text { H } & \text { End } & 5 & 12 & 15 \\\text { I } & \text { End } & 6 & 5 & -\end{array} What is the total cost of reducing this project by two weeks?

Understand the significance of describing the proposed action in a proposal.
Comprehend the main types of appeals in sales messages and provide examples.
Understand and apply the scenario painting technique in creating effective sales messages.
Differentiate between tangible/intangible rewards and intrinsic/extrinsic benefits.

Definitions:

Subpoena Power

The legal authority to compel the production of documents, evidence, or the appearance of witnesses in a court of law or legal proceeding.

Impose Discipline

The act of enforcing rules or standards of behavior and applying penalties for violations to maintain order.

Limited Funding

A situation where financial resources are insufficient to meet the needs or ambitions of a project, organization, or initiative.

Police Corruption

Dishonest or fraudulent conduct by police officers, typically involving bribery or the misuse of power.

Related Questions