The operations manager of a body and paint shop has five cars to schedule for repair. He would like to minimize the throughput time to complete all work on these cars. Each car requires body work prior to painting. The estimates of the times required to do the body paint work on each are as follows:  Car  Body Work  (hrs)   Paint  (hrs)   A 102 B 54 C 75 D 36 E 17\begin{array} { l c c } \text { Car } & \begin{array} { c } \text { Body Work } \\\text { (hrs) }\end{array} & \begin{array} { c } \text { Paint } \\\text { (hrs) }\end{array} \\\hline \text { A } & 10 & 2 \\\text { B } & 5 & 4 \\\text { C } & 7 & 5 \\\text { D } & 3 & 6 \\\text { E } & 1 & 7\end{array} Where in the optimum sequence should car E be scheduled?


Definitions:

Mergers

The process by which two or more companies combine operations, often to increase competitiveness or to expand market share.

Glass-Steagall Act

A law enacted in 1933 to separate commercial banking from investment banking, aimed at reducing conflicts of interest and systemic risks.

Monopolies

Market structures characterized by a single seller dominating a particular market, possessing significant market power over the price and supply of a product or service.

Office of Management and Budget

A division of the Executive Office of the President in the United States that assists the President in preparing the federal budget and overseeing its administration in Executive Branch agencies.

Related Questions