Refer to the following data for jobs waiting to be processed at a single work center (jobs are shown in order of arrival):
 Job  Processing Time ( days ) Due Date  (days from now) A22 B56C610D34E48\begin{array} { l c c } \text { Job } & \begin{array} { c } \text { Processing Time } \\( \text { days } )\end{array} & \begin{array} { c } \text { Due Date } \\\text { (days from now) }\end{array} \\\hline \mathrm { A } & 2 & 2 \\\mathrm {~B} & 5 & 6 \\\mathrm { C } & 6 & 10 \\\mathrm { D } & 3 & 4 \\\mathrm { E } & 4 & 8\end{array} If jobs A, B, and C require two operations each, while jobs D and E require one operation each, what is the schedule sequence using the slack per operation (S/O) priority rule?


Definitions:

True Value

The accurate, fair, or intrinsic worth or importance of something.

Bidders

Individuals or entities that offer a price for goods, services, or assets in an auction or tender process.

Bid-rigging

A form of fraud where competitors collude to inflate prices in procurement bids, undermining fair competition.

Cartels

Associations of independent businesses or organizations that agree to regulate production, pricing, and marketing of goods to maximize profits.

Related Questions