The Operations Manager of a Body and Paint Shop Has

question 113

Multiple Choice

The operations manager of a body and paint shop has five cars to schedule for repair. He would like to minimize the throughput time to complete all work on these cars. Each car requires body work prior to painting. The estimates of the times required to do the body paint work on each are as follows:  Car  Body Work  (hrs)   Paint  (hrs)   A 102 B 54 C 75 D 36 E 17\begin{array} { l c c } \text { Car } & \begin{array} { c } \text { Body Work } \\\text { (hrs) }\end{array} & \begin{array} { c } \text { Paint } \\\text { (hrs) }\end{array} \\\hline \text { A } & 10 & 2 \\\text { B } & 5 & 4 \\\text { C } & 7 & 5 \\\text { D } & 3 & 6 \\\text { E } & 1 & 7\end{array} What is the idle time at the paint work center for the optimal schedule?


Definitions:

Scenario 1-5

A series of hypothetical or planned situations used for strategic planning, decision making, or analysis, labeled numerically for differentiation.

Working

Engaging in a physical or mental activity to achieve an objective, often to earn an income.

Opportunity Cost

The loss of potential gain from other alternatives when one particular option is chosen over others.

Graduate Program

An advanced academic course of study that follows a bachelor's degree, typically culminating in a master's or doctoral degree.

Related Questions