Given the Following Data for Jobs Awaiting Processing at a Manufacturing

question 118

Short Answer

Given the following data for jobs awaiting processing at a manufacturing cell in which jobs are first processed by machine A, then by machine B:
 Process Time (Hours)  Job  Center A  Center B W45X66Y12Z52\begin{array} { c } \quad\quad\quad{ \text { Process Time (Hours) } } \\\begin{array} { l c c } \text { Job } & \text { Center A } & \text { Center B } \\\hline \mathrm { W } & 4 & 5 \\\mathrm { X } & 6 & 6 \\\mathrm { Y } & 1 & 2 \\\mathrm { Z } & 5 & 2\end{array}\end{array} What is the idle time at machine B for the optimum schedule?


Definitions:

National Environmental Policy Act

A U.S. environmental law that promotes the enhancement of the environment and established the President's Council on Environmental Quality (CEQ).

United States Code

The codification by subject matter of the general and permanent laws of the United States, organized into titles by topic.

Citation

A reference to legal authorities and precedents such as statutes, cases, or regulations used to support legal arguments.

Enacted

The process by which proposed laws are officially made into law following approval by a legislative body.

Related Questions