Examlex

Solved

Develop a Material Requirements Plan for End Item P and Its

question 71

Essay

Develop a material requirements plan for end item P and its components, given the following tree. Assume that all lead times are one week, and that lot-for-lot ordering is used except for item F, which is ordered in multiples of 400 units.
One hundred units of P should be available at the start of week 4 and at the start of week 8. Beginning inventories are: 20 Ps, 100 As, and 200 Fs.
Scheduled receipts are: 800 Fs at the start of week 1. Develop a material requirements plan for end item P and its components, given the following tree. Assume that all lead times are one week, and that lot-for-lot ordering is used except for item F, which is ordered in multiples of 400 units. One hundred units of P should be available at the start of week 4 and at the start of week 8. Beginning inventories are: 20 Ps, 100 As, and 200 Fs. Scheduled receipts are: 800 Fs at the start of week 1.


Definitions:

Proactive Socialization

The process in which newcomers play an active role in their own socialization through the use of a number of proactive socialization behaviours.

Experienced Members

People within a group or organization who have accrued significant knowledge or expertise through extended participation or involvement.

Social Aspects

Features related to the interactions, structures, and dynamics within societies and between individuals and groups.

Socialization Tactics

The manner in which organizations structure the early work experiences of newcomers and individuals who are in transition from one role to another.