The Following Information for a Recent Project Was Taken from the Records

question 14

Essay

The following information for a recent project was taken from the records of Green Company:  Processing time 30 days  Inspection time 2 days  Waiting time:  From order receipt until start of production 8 days  From start of production through project completion 2 days  Move time 2.5 days \begin{array} { l r } \text { Processing time } & 30 \text { days } \\\text { Inspection time } & 2 \text { days } \\\text { Waiting time: } & \\\text { From order receipt until start of production } & 8 \text { days } \\\text { From start of production through project completion } & 2 \text { days } \\\text { Move time } & 2.5 \text { days }\end{array} Required:
A. How long did it take to complete the project once production commenced?
B. Compute the manufacturing cycle efficiency.
C. As judged by the cycle efficiency, what percentage of the overall production time was spent on (1) value-adding activities and (2) non-value adding activities?


Definitions:

Routine Requests

Standard inquiries or appeals for information, services, or assistance that follow a common pattern.

Comprehensive Document

A document that covers a topic or subject matter thoroughly, addressing all relevant aspects and details.

Informational Report

A document that presents data and facts without analysis, aiming to inform the reader about a specific topic.

Actionable Effort

Tasks or activities that have a clear objective and can lead to tangible results or outcomes.

Related Questions