In a CPM analysis if you subtract the early finish from the late finish the result is the activity's slack time.


Definitions:

Claim

An assertion, typically unsupported at first, that something is the case, often requiring evidence or argument to be substantiated.

Settlement

The resolution of a dispute or claim, often involving an agreement reached between parties outside of court.

Goodwill Gesture

An action taken to show positive intent, often aimed at strengthening relationships or alleviating conflicts.

Routine Request

A standard or regular solicitation for services, information, or actions that follows an established procedure.