question 76

Multiple Choice

A simple project listing of five activities and their respective time estimates are presented below:  Activity  Immediate Predecessor  Time in Days  A  None 1 B  A 2 C  A 1 D  B and C 3 E  D 2\begin{array}{|l|l|l|}\hline \text { Activity } & \text { Immediate Predecessor } & \text { Time in Days } \\\hline \text { A } & \text { None } & 1 \\\hline \text { B } & \text { A } & 2 \\\hline \text { C } & \text { A } & 1 \\\hline \text { D } & \text { B and C } & 3 \\\hline \text { E } & \text { D } & 2 \\\hline\end{array}
Using the Single Time Estimate CPM procedure,which activities make up the critical path?


Definitions:

Unincorporated Enterprises

Businesses that are not legally separated from their owners, meaning the owner is personally liable for the debts of the business.

Corporate Executives

High-ranking officials within a corporation, responsible for making strategic decisions.

Total Income

The sum of all earnings or revenue received by an individual or an entity, including wages, profits, rents, and other forms of earnings.

Capitalists

Individuals or entities that own capital goods or investments, and use these to produce goods and services for profit.

Related Questions