A Simple Project Listing of Five Activities,their Predecessors and Their

question 31

Multiple Choice

A simple project listing of five activities,their predecessors and their respective time estimates are presented below:  Activity  Immediate Predecessor  Time in Days  A  None 3 B  A 2 C  A 1 D  B and C 3 E  D 4\begin{array} { | l | l | l | } \hline \text { Activity } & \text { Immediate Predecessor } & \text { Time in Days } \\\hline \text { A } & \text { None } & 3 \\\hline \text { B } & \text { A } & 2 \\\hline \text { C } & \text { A } & 1 \\\hline \text { D } & \text { B and C } & 3 \\\hline \text { E } & \text { D } & 4 \\\hline\end{array}
Using CPM,what is the Latest Finish Time for the last activity in this project (i.e. ,the total time to complete the project) ?


Definitions:

Employment Setting

Refers to the place or context in which employment occurs, including physical locations, organizational environments, and remote or virtual workplaces.

Bilateral Contract

A bilateral contract is an agreement in which each of the two parties makes a promise to the other, creating mutual obligations.

Consideration

In contract law, a benefit or something of value that is exchanged between parties to a contract, making the agreement legally binding.

Contracting Party

An entity or individual that enters into a legal contract or agreement.

Related Questions