A Simple Project Listing of Five Activities,their Predecessors and Their

question 53

Multiple Choice

A simple project listing of five activities,their predecessors and their respective time estimates are presented below:  Activity  Immediate Predecessor  Time in Days  A  None 2 B  A 2 C  A 1 D  B and C 3 E  D 1\begin{array} { | l | l | l | } \hline \text { Activity } & \text { Immediate Predecessor } & \text { Time in Days } \\\hline \text { A } & \text { None } & 2 \\\hline \text { B } & \text { A } & 2 \\\hline \text { C } & \text { A } & 1 \\\hline \text { D } & \text { B and C } & 3 \\\hline \text { E } & \text { D } & 1 \\\hline\end{array}
Using the CPM,which activities have slack in this project?


Definitions:

Job Characteristics Model

A framework that posits that five core job characteristics (skill variety, task identity, task significance, autonomy, and feedback) influence job satisfaction and motivation.

Meaningful Work

Work that is perceived as having significance and purpose, often contributing to a greater good or fulfilling personal goals and values.

Work Outcomes

The results or outputs achieved from performing specific tasks or activities in a work environment, often used to assess effectiveness or productivity.

Job Design

The process of defining responsibilities, duties, and tasks in a job to improve productivity and employee satisfaction.

Related Questions