Tower Engineering Corporation is considering undertaking several proposed projects for the next fiscal year.The projects,the number of engineers and the number of support personnel required for each project,and the expected profits for each project are summarized in the following table:
Formulate an integer program that maximizes Tower's profit subject to the following management constraints:
1)Use no more than 175 engineers
2)Use no more than 150 support personnel
3)If either project 6 or project 4 is done,both must be done
4)Project 2 can be done only if project 1 is done
5)If project 5 is done,project 3 must not be done and vice versa
6)No more than three projects are to be done.
Need For Change
The requirement or motivation for making alterations or adjustments in one's personal life, work environment, or society.
Potential Value
The inherent worth or usefulness that something might have under certain conditions, often considered in investments and project planning.
Behaviors
The actions or reactions of individuals or groups in response to external or internal stimuli.
Outside Consultant
An external expert hired to advise on specialized issues or challenges within a company, bringing in fresh perspectives and expertise.
Q6: When an FI sells a loan with
Q18: Canning Transport is to move goods
Q19: The critical path for this network
Q25: Seasonal patterns<br>A)cannot be predicted.<br>B)are regular repeated patterns.<br>C)are
Q28: Henry,a persistent salesman,calls North's Hardware Store once
Q36: The Sanders Garden Shop mixes two
Q36: Generally,the optimal solution to an integer linear
Q48: A businessman is considering opening a
Q55: What are the annual coupon payments promised
Q63: The optimal solution of the linear