During the process to move an organelle inside a cell,the motor protein dynein must bind the organelle and use energy to walk along a microtubule tract.How is the energy to the dynein supplied?


Definitions:

Expected Time

In project management, the average time estimated for the completion of a task or project, considering the most likely, optimistic, and pessimistic scenarios.

CPM Networks

Critical Path Method (CPM) networks are project management tools that map tasks in a project, identifying the longest sequence of dependent tasks (critical path) to determine the shortest project duration.

Project Duration

Project duration is the total time from the initiation to the completion of a project, encompassing all phases of its lifecycle.

Critical Path

The longest sequence of dependent tasks in a project, determining the shortest possible duration to complete the project.