Given the Project Data Below, What Is the Expected Length

question 2

Multiple Choice

Given the project data below, what is the expected length of path A, B, C? Given the project data below, what is the expected length of path A, B, C?   A) 9.0 B) 9.8 C) 9.4 D) 17