The Network Diagram Below Shows the Five Tasks Required to Complete

question 2

Multiple Choice

The network diagram below shows the five tasks required to complete a project and the associated times for those tasks. The network diagram below shows the five tasks required to complete a project and the associated times for those tasks.   What is the latest start date for task C? A) 2 weeks B) 7 weeks C) 6 weeks D) 5 weeks What is the latest start date for task C?