Fee The first step is to calculate the estimated total overhead costs in the two departments.
Machining
Customizing
The second step is to combine the estimated manufacturing overhead costs in the two departments ($44,400 + $21,200 = $65,600) to calculate the plantwide predetermined overhead rate as follow:
The overhead applied to Job C is calculated as follows:
Overhead applied to a particular job = Predetermined overhead rate x Machine-hours incurred by the job
= $6.56 per MH x (4,100 MHs + 1,600 MHs)
= $6.56 per MH x (5,700 MHs)
= $37,392
Job C's manufacturing cost:
Reference: CH02-Ref24
Prather Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on the following data:
Recently, Job P513 was completed with the following characteristics:
-The estimated total manufacturing overhead is closest to:
Task-oriented
A focus on completing tasks or achieving goals, often prioritizing work efficiency over interpersonal relationships.
Boosting Morale
Activities or actions taken to improve the spirit, confidence, or enthusiasm of a group or an individual.
Group Spirit
The sense of solidarity, enthusiasm, and loyalty shared by members within a group, team, or community.
Deliberate
To think about or discuss something very carefully in order to make a decision.
Q17: Montuori Corporation uses a job-order costing system
Q52: Seuell Inc.has provided the following data for
Q76: Stangl Inc.has provided the following data for
Q121: Dr.Johnson hypothesizes that nutrasweet reduces short-term memory.In
Q180: In account analysis, an account is classified
Q196: Entry (4)in the below T-account could represent
Q208: The journal entry to record the allocation
Q224: Purves Corporation is using a predetermined overhead
Q239: The amount of overhead applied to Job
Q243: The unit product cost for Job T687