A line balancing solution has been developed for the assembly line for fertilizer spreaders at Green Grass, Inc.The desired output rate of 30 spreaders per hour will be achieved.The sum of times for all tasks performed on the line is 1200 seconds for each spreader assembled.Which of the following statements must be true?