A Company Is Setting Up an Assembly Line to Produce

question 39

Essay

A company is setting up an assembly line to produce cellular telephones. They intend to use line balancing with the longest-task-time heuristic. They know the demand per hour is 40 phones and the productive time per hour is 54 minutes. Displayed below is the data they have collected regarding task precedence and times. A company is setting up an assembly line to produce cellular telephones. They intend to use line balancing with the longest-task-time heuristic. They know the demand per hour is 40 phones and the productive time per hour is 54 minutes. Displayed below is the data they have collected regarding task precedence and times.    a.What is the cycle time? b.What is the theoretical minimum number of workstations? c.What tasks are assigned to the first workstation? d.How many workstations are needed for the entire line? e.What is the assembly-line efficiency?
a.What is the cycle time?
b.What is the theoretical minimum number of workstations?
c.What tasks are assigned to the first workstation?
d.How many workstations are needed for the entire line?
e.What is the assembly-line efficiency?


Definitions:

Cryptocurrency

A digital or virtual currency that uses cryptography for secure financial transactions, and operates independently of a central bank.

Public Ledger

A ledger available to the public that records all transactions in a network, commonly associated with blockchain technology.

Codec

A device or program that compresses data to enable faster transmission and decompresses received data.

MPEG-4

A method of defining compression of audio and visual (AV) digital data, introduced to provide improved multimedia capabilities.

Related Questions