A Company Has Used PERT for a Project and Wants

question 15

Essay

A company has used PERT for a project and wants to minimize the probability of overrunning a contract deadline of 30 weeks. Three paths of concern in the PERT network have these mean durations and variances in weeks: A company has used PERT for a project and wants to minimize the probability of overrunning a contract deadline of 30 weeks. Three paths of concern in the PERT network have these mean durations and variances in weeks:    a.What is the Z-score for path 1? b.What is the probability of path 2 overrunning the deadline?
a.What is the Z-score for path 1?
b.What is the probability of path 2 overrunning the deadline?


Definitions:

Probability of Success

The likelihood of achieving a desired outcome or event.

Binomial Distribution

A probability distribution that represents the number of successes in a set number of independent binary (success/failure) experiments.

Consecutive Trials

Successive attempts or tests carried out to achieve a particular result, where each trial follows the previous one without interruption.

Possible Outcomes

Refers to all the potential results that could occur from a specified event or experiment.

Related Questions