question 35

Multiple Choice

Cedar Computer Systems Inc.has two projects under consideration and a WACC of 10%.Project Alpha has a hurdle rate of 12% while project Beta has a hurdle rate of 8%.If project Alpha has an expected return of 11% and project Beta has an expected return of 11%,which project(s) ,if any,should the firm accept?