A Project That You Are Considering Today Is Expected to Provide

question 86

Multiple Choice

A project that you are considering today is expected to provide benefits worth $168,000 in one year.If the risk-free rate of interest (rf) is 4.5%,then the value of the benefits of this project today are closest to: