The following computer printout estimated overhead costs using multiple regression:
The following computer printout estimated overhead costs using multiple regression:   During the year the company used 1,000 setup hours and 500 parts. -Refer to the figure.What is the predicted overhead cost? A) $2,500 B) $25,000 C) $75,000 D) $76,000
During the year the company used 1,000 setup hours and 500 parts.
-Refer to the figure.What is the predicted overhead cost?